The building work has come to a welcome halt as it's raining!
I can't complain , because up to today, progress has been really good, the ground floor framing is now complete with the flooring fixed on the 1st floor.
As soon as the weather clears I will get the big fork-lift from Mitre10 to come around and lift the 1st floor framing up, then I will be able to start on the top floor.
I should have the top floor frame up ready for the roof trusses to be fitted by the end of this week (builder promise!)
During this stop I will finalise the stair drawings, making sure they will fit the allocated space.
The making of the stairs should be an interesting project, I plan to make them in our double garage - the garage has never held a car as I took it over as my 'shed'