The piles are set in 400 mm dia x 900 holes and the calcs to fill all the holes will take 10 tonne of builders mix plus Portland cement, all mixed at 6;1
The whole process took me 3 days of very hard work, but I did it!
| 10 Tonnes of Builders Mix! |
| 40 Kg Bag |
| The Cement Measuring System... |
No comments:
Post a Comment